Difference between revisions of "D3-Layman's Report"
(→Indicators of progress (max. 2.000 characters)discuss) |
|||
| (19 intermediate revisions by 3 users not shown) | |||
| Line 1: | Line 1: | ||
| − | + | == Description and methods employed (what, how, where and when) == | |
| − | ==Description and methods employed ( | + | ===What=== |
| − | === | ||
| − | |||
| − | + | This action is devoted to information activities regarding the editing and publishing of the LIFE-IESS Layman's report. | |
| − | |||
| − | + | The objective is to communicate LIFE-IESS project to the general public. | |
| − | + | This action belongs to D - Communication and dissemination actions set of actions. | |
| − | The coordinating beneficiary and associated beneficiaries will acknowledge the support given by the Community using the LIFE logo provided by the Commission. | + | ===How=== |
| + | The contracted professional Communication Agency will be directly involved in this action to editing and publishing 1.500 IESS Layman's report (1 version 5-10 pages long, EN/IT) in ecolabel paper and electronic format. | ||
| + | |||
| + | The Layman's report will be prepared and distributed also during the final event that will be held in Grantorto (PD, IT) on 04/08/2017. | ||
| + | |||
| + | Electronic version will be email to decisions-makers and distributed after the end of the funded period during all possible occasions (seminars, conferences, exhibitions). | ||
| + | |||
| + | The Layman's report will be produce bearing in mind the best LIFE+ examples. | ||
| + | |||
| + | The coordinating beneficiary and associated beneficiaries will acknowledge the support given by the Community using the LIFE logo provided by the Commission. | ||
Methods employed: | Methods employed: | ||
| − | Printed and electronic | + | * Printed and electronic |
| − | === | + | ===Where=== |
| − | |||
| − | + | This action will mainly take place in he project implementation area, i.e. IT | |
| − | |||
| − | + | ===When=== | |
| + | 15/05/17-14/07/17 | ||
| − | ==Constraints and assumptions | + | == Constraints and assumptions == |
| + | * Constraints | ||
| + | ** Information must be rendered in an immediately comprehensible way to citizens. | ||
| + | * Assumptions | ||
| + | ** No extraordinary events happen in coincidence of LIFE-IESS communication effort that will significantly shadow the interest of the issue. | ||
| − | + | == Beneficiary responsible for implementation == | |
| − | + | The beneficiary responsible for overall implementation of Action D3-Layman's Reports is GRANT. | |
| − | |||
| − | |||
| − | == | + | == Expected results == |
| + | *1 Layman's report edited, published and distributed | ||
| − | The | + | == Indicators of progress == |
| + | * The main indicator is (1) Fulfilment | ||
| + | *The measuring will be carried out by GRANT at activity end | ||
| + | *The threshold is ON/OFF (Layman’s report) | ||
| − | == | + | ==Deliverable products== |
| − | |||
| − | |||
| − | + | *DD3.2 - Layman's report (IT/EN) 1500 | |
| − | + | ==Milestones== | |
| − | + | *M17 - Layman's report ready (09/06/17) | |
| − | + | ||
| + | ==Timetable== | ||
| + | For each project action, please tick the corresponding Period. | ||
| + | |||
| + | D3 - Layman's Report 46 days? 07/04/17 - 09/06/17 | ||
[[Index:LIFE|Torna all'indice]] | [[Index:LIFE|Torna all'indice]] | ||
| + | |||
| + | [[Category:Communication_and_dissemination_actions]] | ||
Latest revision as of 23:05, 19 September 2012
Contents
Description and methods employed (what, how, where and when)[edit]
What[edit]
This action is devoted to information activities regarding the editing and publishing of the LIFE-IESS Layman's report.
The objective is to communicate LIFE-IESS project to the general public.
This action belongs to D - Communication and dissemination actions set of actions.
How[edit]
The contracted professional Communication Agency will be directly involved in this action to editing and publishing 1.500 IESS Layman's report (1 version 5-10 pages long, EN/IT) in ecolabel paper and electronic format.
The Layman's report will be prepared and distributed also during the final event that will be held in Grantorto (PD, IT) on 04/08/2017.
Electronic version will be email to decisions-makers and distributed after the end of the funded period during all possible occasions (seminars, conferences, exhibitions).
The Layman's report will be produce bearing in mind the best LIFE+ examples.
The coordinating beneficiary and associated beneficiaries will acknowledge the support given by the Community using the LIFE logo provided by the Commission.
Methods employed:
- Printed and electronic
Where[edit]
This action will mainly take place in he project implementation area, i.e. IT
When[edit]
15/05/17-14/07/17
Constraints and assumptions[edit]
- Constraints
- Information must be rendered in an immediately comprehensible way to citizens.
- Assumptions
- No extraordinary events happen in coincidence of LIFE-IESS communication effort that will significantly shadow the interest of the issue.
Beneficiary responsible for implementation[edit]
The beneficiary responsible for overall implementation of Action D3-Layman's Reports is GRANT.
Expected results[edit]
- 1 Layman's report edited, published and distributed
Indicators of progress[edit]
- The main indicator is (1) Fulfilment
- The measuring will be carried out by GRANT at activity end
- The threshold is ON/OFF (Layman’s report)
Deliverable products[edit]
- DD3.2 - Layman's report (IT/EN) 1500
Milestones[edit]
- M17 - Layman's report ready (09/06/17)
Timetable[edit]
For each project action, please tick the corresponding Period.
D3 - Layman's Report 46 days? 07/04/17 - 09/06/17