Description and methods employed (what, how, where and when)[edit]

What[edit]

Project management aims at ensuring that project objectives are adequately achieved, on time and within the costs estimated. It also allows effective decision-making and smooth communication among partners and with the EC. It assures that project progress reports and cost statements are provided timely and accurately. This action includes all activities undertaken by the beneficiaries for the management of the project (administrative, technical and financial aspects) and for meeting the reporting and accountability obligations. The objective is to have the full control of project activities, to intervene promptly in order to give the EC the certainty of a sound management of contractual issues and to give clear indications to project staff about management rules.

Planning, monitoring, quality assurance will be implemented by: running the technical management of work packages; maintaining and adjusting as needed LIFE-IESS plans; monitoring pace and quality of the project; managing the different project's activities, securing internal communication and interacting among partners for the definition and detailed plan of the activities they lead; identifying problems; contingency planning; taking appropriate actions at proportional level; organizing and chairing LIFE-IESS meetings; fostering gender equality; defining and managing the bridging of the project beyond the LIFE+ contract term.

Administration and communication will be implemented by: supplying all deliverables to the EC, providing financial control, subcontracting and legal documentation, and maintaining the execution of the LIFE-IESS Partnership Agreement (Consortium Agreement), managing distribution of funding to the Associated Beneficiaries, informing and reporting the EC about the project's activities, secure and provide all deliverables, including the preparation of the Inception report, the progress reports, the mid-term and final reports with payment request, providing the LIFE-IESS interface with EC and other relevant parties, assisting to relevant EC events, setting up and maintaining an internal documentation digital workspace for LIFE-IESS, members, promoting gender equality in the project, ensuring effective coordination of knowledge management.

How[edit]

This action is organised into two different tasks: (1) Manage LIFE-IESS technical, financial, legal and administrative aspect; (2) Define and run project performance monitoring.

Project Coordination provides good overall strategic direction at the environmental, technical and management levels, while ensuring that LIFE-IESS is running smoothly, that problems are taken care of, reports written and that all parties involved in the project receives support.

The Project Manager is the principal owner of this Action. The candidate project manager is Architetto Andrea Bordignon.

The management structure is presented in the annexed Management Chart.

IESS Managamen Chart

The meetings of the Project Management Committee (Steering Meetings) are the main agora for important decisions.

The Steering Committee is composed by a representative for each partner and is involved with recommendations regarding the adherence to the plan and the partners’ responsibility as to the proper execution of the assigned activity. Each representative shall have one vote and may appoint a substitute to attend and vote at any meeting. The SC shall not deliberate and decide validly unless at least half (1/2) of its members are present or represented. Where decisions are to be taken unanimously, all Participants must be present or represented at the meeting. Given that the Coordinating Beneficiary is the sole responsible of the contract face the EC, GRANT chairs the committee with veto power and double vote weight if there is not a majority.

More detailed provisions for the management of the project will be drawn in the Consortium Agreement that will be signed among Beneficiaries following EC prescriptions.

Steering Committees will be held every 6-9 months as the crucial and formal coordination tool. Day-to-day collaboration and coordination will be maintained directly and also through the private area of the IESS website for managing project activities. Foreseen dates of face-to-face Steering Committees are: 03/12/13, 04/06/14, 18/12/14, 03/07/15, 16/01/16, 02/08/16, 18/01/17, 06/07/17, 02/09/13.

Each partner will also designate an activity leader who will be in staff to the PM, oversee the work related to assigned actions and is in charge of producing project deliverables.

The monitoring will be conducted by the Project Manager and other technical resources who collaborate in the activity against LIFE-IESS plan on day-to-day basis and technical monitoring project review meetings to verify general progress against overall plan and financial considerations.

A careful planning of the organization of monitoring activities (including areas of responsibility and authority) will ensure that everyone works together for a smoothly run project. Progress of the project work will be monitored against the milestones and the objectives defined in a monitoring plan. Monitoring plan will provide the use of measures to review and evaluate the project, in order to ensure that keeps on track. At the end of the Project, the Monitoring plan will include an evaluation and reflection step in order to gather the most important lessons learned.

Please see also C1 and C2.

Reporting and Administration deals with reporting and financial procedures under LIFE+ provisions and overarching EU and national law. An Inception Report will be prepared within nine month from project start (14/04/2014). The Inception Report will contains an assessment as to whether the project objectives and work plan are still valid at that time, to give the Commission the possibility to launch an early termination procedure if the project's objectives are not achievable or the work plan is not feasible. The other mandatory reports will be completed as follows: Mid-term report with payment request(15/09/15); Progress Report (15/02/17), Final Report and payment request (30/11/17), Audit Report (30/11/17)

Reports from the Monitoring and evaluation Action C1, C2 are prepared independently but will be forwarded to the Commission through this function.

Contract and Legal task will deal with all contractual and other legal issues of the project (Consortium Agreement implementation and amendments, relationships with third parties, change control and formalisation of updates to the work plan, roles and resources assignment). A quality approach will be applied to all the work undertaken drawing up an agenda for quality as a regular part of each meeting of the Steering Committees.

The Project Manager will: provide the LIFE-IESS project interface with the Commission, follow the project to ensure timely execution of work, achievement of milestones and deliverables, monitor and ensure the quality of deliverables, manage review meetings, manage decisions regarding common funds, changes to plans.

The Coordinating Beneficiary appoints the Financial Officer who is responsible of payments. The Financial Officer is responsible of the faultlessness of financial transactions within the project. The Financial Officer executes the payment orders committed by the Project Manager. The Financial Officer reports to the Coordinating Beneficiary. For each Action there one responsible Beneficiary, even in the case that more Beneficiaries participate to that Action's activities.

Methods employed:

  • Project Management methods (PMBOK 4th, Agile approach)
  • participatory approaches
  • steering committees
  • reporting
  • administrative/financial rules
  • quality approaches

Where[edit]

Project Management activities will mainly take place at the Coordinating Beneficiary facilities (IT). Activities that are in charge of Associated Beneficiaries will take place at their facilities. If requested, the Project Manager and another project officer will attend to the regional kick-off meeting with EC representatives at the places indicated by the Commission.


When[edit]

02/09/13 -31/08/17


Constraints and assumptions[edit]

  • Constraints
    • from Grant Agreement, Special Provisions and relevant rules governing the Contract;
    • from regulations and laws governing the scope of the project.
  • Assumptions
    • no disrupting organisational change will occur in partner organisations across project duration;
    • partners' institutional mandates do not substantially change across project duration;
    • turnover of key persons is low.

Beneficiary responsible for implementation[edit]

The Beneficiary responsible is GRANT.

Expected results[edit]

The main results are:

  • Sound project management and accountability
  • Quality control of the outcomes delivered to the Commission and the stakeholders
  • Decision making and conflict resolution capacity.

Accordingly the following outputs will result:

  • All project deliverables/outputs supplied in due time, quantity and quality.
  • All contract provisions satisfactorily fulfilled.
  • No serious conflict relevant to the project arises among partners
  • Financial management of the project traceable through transparent records.
  • Project partners and key stakeholders committed to prosecute on the project's track after its subventioned term.

Indicators of progress[edit]

The main indicators are:

  • formal compliance with the contract,
  • the substantial compliance with the contract and
  • the focus on project objectives.

The dimensions involved are both legal and value for money.

The measuring will be accomplished by GRANT: the first to be carried out progress, interim and final report delivery the last one at project end.

For the first indicator, the threshold is a zero non-compliance notices and the means of verification is document review.

For the second indicator, the threshold is that all deliverables will be sent and 90% of due results available.

The means of verification is document review.

For the focus on project objectives, the threshold is that all objectives must be achieved and the means of verification is document review.

Deliverable products[edit]

  • DE1.1 - Consortium Agreement (11/10/13)
  • OR - Inception Report (14/04/14)
  • OR - Mid-term report with payment request (15/09/15)
  • OR - Progress Report(15/02/17)
  • OR - Final Report and payment request (30/11/17)
  • OR - Audit Report (30/11/17)

Milestones[edit]

M20 - Consortium Agreement signed (11/10/13)


Timetable[edit]

For each project action, please tick the corresponding Period.

E1 - Project management by Comune di Grantorto 1.044 days? 02/09/13-31/08/17