Difference between revisions of "E2-Networking activities"
| Line 10: | Line 10: | ||
*Participate to initiative organised by the EC to foster collaboration among projects. | *Participate to initiative organised by the EC to foster collaboration among projects. | ||
| − | The link with communities working on | + | The link with communities working on climate change resilience is of fundamental relevance. Of course all this in addition to the communities dealing with adaptation, and environmental issues. |
| − | The project will seek to establish associations and active cooperation with national, European | + | The project will seek to establish associations and active cooperation with national, European and international networks. |
This action belongs to the E - Project management and monitoring of project progress set of actions. | This action belongs to the E - Project management and monitoring of project progress set of actions. | ||
| Line 35: | Line 35: | ||
===Where=== | ===Where=== | ||
| − | Networking activities will take place in the project implementation area, i.e. IT | + | Networking activities will take place in the project implementation area, i.e. IT. |
Participation to/organisation of networking activity in other European countries is also envisaged. The cost incurred by this activity (including 2 or 3 European trips for xxxx the partner more involved in such activities) is budgeted. | Participation to/organisation of networking activity in other European countries is also envisaged. The cost incurred by this activity (including 2 or 3 European trips for xxxx the partner more involved in such activities) is budgeted. | ||
| Line 41: | Line 41: | ||
===When=== | ===When=== | ||
| − | + | 25/11/13-30/06/17 | |
| + | |||
== Constraints and assumptions == | == Constraints and assumptions == | ||
| Line 56: | Line 57: | ||
== Beneficiary responsible for implementation == | == Beneficiary responsible for implementation == | ||
| − | The beneficiary responsible for E3-Networking activities is | + | The beneficiary responsible for E3-Networking activities is GRANT. |
== Expected results == | == Expected results == | ||
| Line 65: | Line 66: | ||
*permanent collaboration has been established with 3 networks at European dimension working on relevant issues. | *permanent collaboration has been established with 3 networks at European dimension working on relevant issues. | ||
| − | |||
| − | * | + | == Indicators of progress == |
| + | The main indicators are | ||
| + | *Level of networking and | ||
| + | *Fulfilment. | ||
| − | + | The measuring will be carried out by GRANT: at reporting time and at activity end. | |
| − | |||
For the networking the threshold will be at least 3 permanent collaborations established. | For the networking the threshold will be at least 3 permanent collaborations established. | ||
| Line 79: | Line 81: | ||
==Deliverable products== | ==Deliverable products== | ||
| + | DE2.1 - Final report on networking activities(30/06/17) | ||
| + | |||
==Milestones== | ==Milestones== | ||
| + | M21 - Checkpoint on networking activities (16/01/15) | ||
==Timetable== | ==Timetable== | ||
For each project action, please tick the corresponding Period. | For each project action, please tick the corresponding Period. | ||
| + | |||
| + | E2 - Networking activities 940 days? 25/11/13 -30/06/17 | ||
| + | |||
[[Index:LIFE|Torna all'indice]] | [[Index:LIFE|Torna all'indice]] | ||
Revision as of 23:24, 19 September 2012
Contents
Description and methods employed (what, how, where and when)
What
E2 Networking includes all the activities related to the networking of LIFE-IESS project, in view of adding European value and widening its scope and sustainability after the EC funded period.
The connections with other relevant projects communities (LIFE, FP7, etc.) will also contribute to involve and establish durable links and reinforce LIFE-IESS concept amid relevant communities. The main objectives of the action are to:
- Establish regular collaboration with existing thematic networks
- Participate to initiative organised by the EC to foster collaboration among projects.
The link with communities working on climate change resilience is of fundamental relevance. Of course all this in addition to the communities dealing with adaptation, and environmental issues.
The project will seek to establish associations and active cooperation with national, European and international networks.
This action belongs to the E - Project management and monitoring of project progress set of actions.
How
- Participation and/or contribution to networks, events and information platforms organised by EC;
- Establishing contacts and regular information exchange with other projects dealing with the same or similar issues;
- Sign into existing networks in the same field of action
- Exchange of results, information and best practices
- Participation to event organized by other relevant project communities
- Exchanges and visits
Methods employed:
- Web based collaboration
- RSS feeds
- Screening of existing initiatives
- Maintaining of a registry and calendar of subscribed initiatives
- Screening of information sources
- Mail contacts
- Regular delivery of information
Where
Networking activities will take place in the project implementation area, i.e. IT.
Participation to/organisation of networking activity in other European countries is also envisaged. The cost incurred by this activity (including 2 or 3 European trips for xxxx the partner more involved in such activities) is budgeted.
When
25/11/13-30/06/17
Constraints and assumptions
- Constraints
- Initiatives to which the LIFE-IESS Partnership contributes must focus on the pertinent themes
- Only original contribution of the project will be delivered
- References, sources, directories etc. will be made available through the project web site
- Networks to which the partnership participates must be focussed on themes next to LIFE-IESS ones
- Assumptions
- Existing relevant initiatives are open for LIFE-IESS participation.
- Networks are willing to include new partners.
Beneficiary responsible for implementation
The beneficiary responsible for E3-Networking activities is GRANT.
Expected results
The main results are:
- LIFE-IESS included in the top 3 attaining initiatives/networks
- LIFE-IESS contribution are regularly published and well ranked
- permanent collaboration has been established with 3 networks at European dimension working on relevant issues.
Indicators of progress
The main indicators are
- Level of networking and
- Fulfilment.
The measuring will be carried out by GRANT: at reporting time and at activity end.
For the networking the threshold will be at least 3 permanent collaborations established.
For the completion report the threshold is ON/OFF.
The mean of verification is document review.
Deliverable products
DE2.1 - Final report on networking activities(30/06/17)
Milestones
M21 - Checkpoint on networking activities (16/01/15)
Timetable
For each project action, please tick the corresponding Period.
E2 - Networking activities 940 days? 25/11/13 -30/06/17