Description and methods employed (what, how, where and when)

What

Action 2 is a clearance action ensuring that all subjects and objects of the project have the necessary permission granted and that there is no obstacles to project's further developments.

The action makes sure that all conditions for moving to the implementation phase are met and on time. We remark that, the IESS implementation activities do not require special permissions. Potentially, however, it should be necessary to verify if there are procedures to meet or organism to be informed.

This action belongs to A – Preparatory set of actions.

How

Once the ideas on local needs and resources are more precise, the development of a first hypothesis of a local strategy for mitigation and adaptation framed, and some main themes of interest (water, soil, energy, mobility) detected and discussed with stakeholders, the partners will go through detailed engineering studies to making a concrete analysis of the initiatives to be developed.

At this stage, particular attention will be paid to the identification of conflicts, or legal problems, for example, relating to contracts or incentives.

An environmental assessment analysis (on the basis of Directive 85/337/EEC, 'Environmental Impact Assessment' – EIA Directive and 2001/42/EC 'Strategic Environmental Assessment' – SEA Directive) will be undertaken. It will allow to highlight all the basic elements to go to the implementation phase. This way, the implications of IESS decisions will be taken into due consideration and account before following actions will start. Environmental assessment enables environmental factors to be given due weight, along with economic or social factors. It helps to promote a sustainable pattern and it benefits all those involved in the planning process.

From the project's partners point of view, the preparation of an environmental statement in parallel with project design, provides an useful framework within which environmental considerations and design development can interact. Environmental analysis may indicate ways in which the implementation plan can be modified to avoid possible adverse effects, for example through considering alternatives. Taking these steps is likely to make the demonstration stages run more smoothly.

The advisory opinion of Climate change Committees , when plans are still fluid, can enable to make adjustments which will help to secure a smoother passage for the proposed execution phase and result in a better outcome.

It should be noted that an outline of the main alternative approaches to the proposed development and the main reasons for their choice will be included in the analysis that will also include a contingency planning.

In parallel, controls on the need to request permissions will be verified: it can also be simply the necessity to comply with certain administrative procedures (if there is an agreement between two Municipalities this is neither a permit nor a license but a process that must still be acquitted).

The D2.2 - Reviewed GO report (26/09/2014) is the clearance report assessing that all needed authorisations are obtained in time (no doubts they are given). The main risk of this action is delay (for instance in the case that the procedure to cross a private area takes 4 months instead of 2 months). For this reason, the partership agrees to introduce a buffer period, extending the duration of the activity to the to avoid any kind of problems.

Methods employed:

  • engineering studies
  • environmental assessment procedures
  • legal advices about contracts and agreements

Where

This action will mainly take place in the project implementation area, i.e. IT.

When

17/02/14-26/09/14

Constraints and assumptions

  • Constraints
    • Timeliness
  • Assumptions
    • The environmental legal and authorisation framework will continue to evolve following the current trend
    • Permits are a straightforward procedure
    • Mandates and current agreements among beneficiaries do not substantially change across project duration

Beneficiary responsible for implementation

The beneficiary responsible for implementation is FONTA. The other partners participate in the action.

Expected results

Principal results of this actions are

  • 3 Detailed engineering studies
  • Permits for demonstration activities and works

Indicators of progress

  • Performance
    • Delivery of compliant outputs: preliminary project, tender documents, permits and detailed projects
    • Quality of delivered outputs: completeness and appropriateness (assessed by the project management team). The threshold is that no formal complaint is raised)
  • Schedule and effort variance;
    • actual vs. planned start/duration of tasks (if lag time reserved for contingency is to be used then remediation actions must be triggered);
    • actual vs. planned resource use (15% work overload and 5% budget variance are thresholds for triggering remediation actions)

Deliverable products

The A2 deliverables are: D2.1 - Detailed Engineering and Environmental Studies (26/09/2014) D2.2 - Reviewed GO report (26/09/2014)

Milestones

M3 - Permits and authorisation procedures completed (26/09/2014)

Timetable

For each project action, please tick the corresponding Period.

A2 - Paperwork 160 days? 17/02/14 26/09/14