Difference between revisions of "E1-Project management by Comune di Grantorto"
(Created page with "== Description and methods employed (what, how, where and when) == ===What=== ===How=== Methods employed: * * * ===Where=== This action will mainly take place in ............") |
|||
| Line 1: | Line 1: | ||
== Description and methods employed (what, how, where and when) == | == Description and methods employed (what, how, where and when) == | ||
===What=== | ===What=== | ||
| + | Project management aims at ensuring that project objectives are adequately achieved, on time and within the costs estimated. It also allows effective decision-making and smooth communication among partners and with the EC. It assures that project progress reports and cost statements are provided timely and accurately. This action includes all activities undertaken by the beneficiaries for the management of the project (administrative, technical and financial aspects) and for meeting the reporting and accountability obligations. The objective is to have the full control of project activities, to intervene promptly in order to give the EC the certainty of a sound management of contractual issues and to give clear indications to project staff about management rules. | ||
| + | Planning, monitoring, quality assurance will be implemented by: running the technical management of work packages; maintaining and adjusting as needed LIFE-IESS plans; monitoring pace and quality of the project; managing the different project's activities, securing internal communication and interacting among partners for the definition and detailed plan of the activities they lead; identifying problems; taking appropriate actions at proportional level; organizing and chairing LIFE-IESS meetings; fostering gender equality; defining and managing the bridging of the project beyond the LIFE+ contract term. | ||
| + | |||
| + | Administration and communication will be implemented by: supplying all deliverables to the EC, providing financial control, subcontracting and legal documentation, and maintaining the execution of the LIFE-IESS Partnership Agreement (Consortium Agreement), managing distribution of funding to the Associated Beneficiaries, informing and reporting the EC about the project's activities, secure and provide all deliverables, including the preparation of the Inception report, the progress reports, the mid-term and final reports with payment request, providing the LIFE-IESS interface with EC and other relevant parties, assisting to relevant EC events, setting up and maintaining an internal documentation digital workspace for LIFE-IESS, members, promoting gender equality in the project, ensuring effective coordination of knowledge management. | ||
===How=== | ===How=== | ||
| + | This action is organised into two different tasks: (1) Manage LIFE-IESS technical, financial, legal and administrative aspect; (2) Define and run project performance monitoring. | ||
| + | |||
| + | The Project Manager is the principal owner of this Action. The candidate project manager is xxxxxxxxxxxxxx | ||
| + | |||
| + | The management structure is presented in the annexed Management Chart. | ||
| + | |||
| + | The meetings of the Project Management Committee (Steering Meetings) are the main agora for important decisions. | ||
| + | |||
| + | Project Coordination provides good overall strategic direction at the environmental, technical and management levels, while ensuring that LIFE-IESS is running smoothly, that problems are taken care of, reports written and that all parties involved in the project receives support. | ||
| + | |||
| + | Steering Committees will be held every 6-9 months as the crucial and formal coordination tool. Day-to-day collaboration and coordination will be maintained directly and also through the virtual environment for managing project activities (a web based project portal with rich-media capabilities). Foreseen dates of face-to-face Steering Committees are ........... The monitoring will be conducted by the Project Manager and other technical resources who collaborate in the activity against LIFE-IESS plan on day-to-day basis and technical monitoring project review meetings to verify general progress against overall plan and financial considerations. | ||
| + | |||
| + | A careful planning of the organization of monitoring activities (including areas of responsibility and authority) will ensure that everyone works together for a smoothly run project. Progress of the project work will be monitored against the milestones and the objectives defined in the Monitoring Plan. The Monitoring plan will include for each object of monitoring a specific description of the reason for measuring that given fact, or product, or result associating them to the relevant interests of stakeholders/participants. For each monitoring item, methods used will be described along with their references. Moreover, timing (how often each data collected and when), responsibilities (who is responsible for making sure the monitoring happens), threshold for compliance, and data restitution formats will be included. | ||
| + | |||
| + | Monitoring plan will provide the use of measures to review and evaluate the project, in order to ensure that keeps on track. At the end of the Project, the Monitoring plan will include an evaluation and reflection step in order to gather the most important lessons learned. | ||
| + | |||
| + | Please see also C1, C2 and C3. | ||
| + | |||
| + | Reporting and Administration deals with reporting and financial procedures under LIFE+ provisions and overarching EU and national law. An Inception Report will be prepared within nine month from project start. The Inception Report will contains an assessment as to whether the project objectives and work plan are still valid at that time, to give the Commission the possibility to launch an early termination procedure if the project's objectives are not achievable or the work plan is not feasible. Reports from the Monitoring and evaluation Action C1, C2, C3 are prepared independently but will be forwarded to the Commission through this function. | ||
| + | |||
| + | Contract and Legal task will deal with all contractual and other legal issues of the project (Consortium Agreement implementation and amendments, relationships with third parties, change control and formalisation of updates to the work plan, roles and resources assignment). A quality approach will be applied to all the work undertaken drawing up an agenda for quality as a regular part of each meeting of the Steering Committees. | ||
| + | |||
| + | The Project Manager will: provide the LIFE-IESS project interface with the Commission, follow the project to ensure timely execution of work, achievement of milestones and deliverables, monitor and ensure the quality of deliverables, manage review meetings, manage decisions regarding common funds, changes to plans. | ||
| + | |||
| + | The Coordinating Beneficiary appoints the Financial Officer who is responsible of payments. The Financial Officer is responsible of the faultlessness of financial transactions within the project. The Financial Officer executes the payment orders committed by the Project Manager. The Financial Officer reports to the Coordinating Beneficiary. The project work has been allotted to Actions. For each Action there one responsible Beneficiary, even in the case that more Beneficiaries participate to that Action's activities. | ||
Methods employed: | Methods employed: | ||
| − | + | ||
| − | + | This Action is inspired by a lean approach based on a participatory approach based on clear responsibility. More detailed provisions for the management of the project will be drawn in the Partnership Agreement that will be signed among Beneficiaries following EC prescriptions. | |
| − | + | ||
| + | Each Beneficiary has one seat in the Steering Committee, which is the organism where decisions that involve legal representation powers are taken. Given that the Coordinating Beneficiary is the sole responsible of the contract face the EC, xxxxx chairs the committee with veto power and double vote weight if there is not a majority. | ||
===Where=== | ===Where=== | ||
Revision as of 16:05, 23 August 2012
Contents
Description and methods employed (what, how, where and when)
What
Project management aims at ensuring that project objectives are adequately achieved, on time and within the costs estimated. It also allows effective decision-making and smooth communication among partners and with the EC. It assures that project progress reports and cost statements are provided timely and accurately. This action includes all activities undertaken by the beneficiaries for the management of the project (administrative, technical and financial aspects) and for meeting the reporting and accountability obligations. The objective is to have the full control of project activities, to intervene promptly in order to give the EC the certainty of a sound management of contractual issues and to give clear indications to project staff about management rules.
Planning, monitoring, quality assurance will be implemented by: running the technical management of work packages; maintaining and adjusting as needed LIFE-IESS plans; monitoring pace and quality of the project; managing the different project's activities, securing internal communication and interacting among partners for the definition and detailed plan of the activities they lead; identifying problems; taking appropriate actions at proportional level; organizing and chairing LIFE-IESS meetings; fostering gender equality; defining and managing the bridging of the project beyond the LIFE+ contract term.
Administration and communication will be implemented by: supplying all deliverables to the EC, providing financial control, subcontracting and legal documentation, and maintaining the execution of the LIFE-IESS Partnership Agreement (Consortium Agreement), managing distribution of funding to the Associated Beneficiaries, informing and reporting the EC about the project's activities, secure and provide all deliverables, including the preparation of the Inception report, the progress reports, the mid-term and final reports with payment request, providing the LIFE-IESS interface with EC and other relevant parties, assisting to relevant EC events, setting up and maintaining an internal documentation digital workspace for LIFE-IESS, members, promoting gender equality in the project, ensuring effective coordination of knowledge management.
How
This action is organised into two different tasks: (1) Manage LIFE-IESS technical, financial, legal and administrative aspect; (2) Define and run project performance monitoring.
The Project Manager is the principal owner of this Action. The candidate project manager is xxxxxxxxxxxxxx
The management structure is presented in the annexed Management Chart.
The meetings of the Project Management Committee (Steering Meetings) are the main agora for important decisions.
Project Coordination provides good overall strategic direction at the environmental, technical and management levels, while ensuring that LIFE-IESS is running smoothly, that problems are taken care of, reports written and that all parties involved in the project receives support.
Steering Committees will be held every 6-9 months as the crucial and formal coordination tool. Day-to-day collaboration and coordination will be maintained directly and also through the virtual environment for managing project activities (a web based project portal with rich-media capabilities). Foreseen dates of face-to-face Steering Committees are ........... The monitoring will be conducted by the Project Manager and other technical resources who collaborate in the activity against LIFE-IESS plan on day-to-day basis and technical monitoring project review meetings to verify general progress against overall plan and financial considerations.
A careful planning of the organization of monitoring activities (including areas of responsibility and authority) will ensure that everyone works together for a smoothly run project. Progress of the project work will be monitored against the milestones and the objectives defined in the Monitoring Plan. The Monitoring plan will include for each object of monitoring a specific description of the reason for measuring that given fact, or product, or result associating them to the relevant interests of stakeholders/participants. For each monitoring item, methods used will be described along with their references. Moreover, timing (how often each data collected and when), responsibilities (who is responsible for making sure the monitoring happens), threshold for compliance, and data restitution formats will be included.
Monitoring plan will provide the use of measures to review and evaluate the project, in order to ensure that keeps on track. At the end of the Project, the Monitoring plan will include an evaluation and reflection step in order to gather the most important lessons learned.
Please see also C1, C2 and C3.
Reporting and Administration deals with reporting and financial procedures under LIFE+ provisions and overarching EU and national law. An Inception Report will be prepared within nine month from project start. The Inception Report will contains an assessment as to whether the project objectives and work plan are still valid at that time, to give the Commission the possibility to launch an early termination procedure if the project's objectives are not achievable or the work plan is not feasible. Reports from the Monitoring and evaluation Action C1, C2, C3 are prepared independently but will be forwarded to the Commission through this function.
Contract and Legal task will deal with all contractual and other legal issues of the project (Consortium Agreement implementation and amendments, relationships with third parties, change control and formalisation of updates to the work plan, roles and resources assignment). A quality approach will be applied to all the work undertaken drawing up an agenda for quality as a regular part of each meeting of the Steering Committees.
The Project Manager will: provide the LIFE-IESS project interface with the Commission, follow the project to ensure timely execution of work, achievement of milestones and deliverables, monitor and ensure the quality of deliverables, manage review meetings, manage decisions regarding common funds, changes to plans.
The Coordinating Beneficiary appoints the Financial Officer who is responsible of payments. The Financial Officer is responsible of the faultlessness of financial transactions within the project. The Financial Officer executes the payment orders committed by the Project Manager. The Financial Officer reports to the Coordinating Beneficiary. The project work has been allotted to Actions. For each Action there one responsible Beneficiary, even in the case that more Beneficiaries participate to that Action's activities.
Methods employed:
This Action is inspired by a lean approach based on a participatory approach based on clear responsibility. More detailed provisions for the management of the project will be drawn in the Partnership Agreement that will be signed among Beneficiaries following EC prescriptions.
Each Beneficiary has one seat in the Steering Committee, which is the organism where decisions that involve legal representation powers are taken. Given that the Coordinating Beneficiary is the sole responsible of the contract face the EC, xxxxx chairs the committee with veto power and double vote weight if there is not a majority.
Where
This action will mainly take place in ..............
When
00/00/00-00/00/00
Constraints and assumptions
- Constraints
- Assumptions
Beneficiary responsible for implementation
Expected results
Principal results of monitoring the project impact on the main target audience are: